Complaint Review: Superior Mechanical Systems, Inc. - Pinellas Park Select State/Province
- Superior Mechanical Systems, Inc. 6482 Park Blvd. Pinellas Park, Select State/Province USA
- Phone: 727-548-1711
- Web: http://www.superiormechanical.net
- Category: Builders & Contractors
Superior Mechanical Systems, Inc. superiormechanical.net Non payment of Sub contractors Lein Pinellas Park flordia
*REBUTTAL Owner of company: Payment / Termination
*UPDATE Employee ..inside information: Payment Terms
*UPDATE Employee: Payment / Termination
Non payment of Sub contractors Lein on job and G.C. 5500.00 non payment..
This report was posted on Ripoff Report on 07/24/2013 07:22 AM and is a permanent record located here: https://www.ripoffreport.com/reports/superior-mechanical-systems-inc/pinellas-park-select-stateprovince-33781/superior-mechanical-systems-inc-superiormechanicalnet-non-payment-of-sub-contractors-l-1069606. The posting time indicated is Arizona local time. Arizona does not observe daylight savings so the post time may be Mountain or Pacific depending on the time of year. Ripoff Report has an exclusive license to this report. It may not be copied without the written permission of Ripoff Report. READ: Foreign websites steal our content
If you would like to see more Rip-off Reports on this company/individual, search here:



#3 REBUTTAL Owner of company
Payment / Termination
AUTHOR: SMSystems - ()
SUBMITTED: Friday, August 02, 2013
Patrick McKenna of 3D Specialist was contracted by Superior Mechanical Systems to perform coordinated HVAC shop drawings with a payment schedule that was mutually agreed to in writing: $3,000 upon receipt of shop drawings, $3,500 upon approval of drawings, $3,500 upon receipt of as-builts.
To date, 3D Specialists was paid $3,500 for initial drawings ($500 more than the schedule amount), 3D Specialists was contractually obligated to make necessary adjustments so that the Engineer approval would be obtained prior to receiving further progress payments.
He refused, demand to be paid up front. 3D Specialist’s contract was terminated for failure to perform.

#2 UPDATE Employee
Payment / Termination
AUTHOR: SMSystems - ()
SUBMITTED: Wednesday, July 31, 2013
Patrick McKenna of 3D Specialist was contracted to perform coordinated HVAC shop drawings with a payment schedule that was mutually agreed to in writing: $3,000 upon receipt of shop drawings, $3,500 upon approval of drawings, $3,500 upon receipt of as-builts.
To date, 3D Specialists was paid $3,500 for initial drawings ($500 more than the schedule amount), 3D Specialists was contractually obligated to make necessary adjustments so that the Engineer approval would be obtained prior to receiving further progress payments.
He refused, demand to be paid up front. 3D Specialist’s contract was terminated for failure to perform.

#1 UPDATE Employee ..inside information
Payment Terms
AUTHOR: SMSystems - ()
SUBMITTED: Wednesday, July 31, 2013
Patrick McKenna of 3D Specialist was contracted to perform coordinated HVAC shop drawings with a payment schedule that was mutually agreed to in writing: $3,000 upon receipt of shop drawings, $3,500 upon approval of drawings, $3,500 upon receipt of as-builts.
To date, 3D Specialists was paid $3,500 for initial drawings ($500 more than the schedule amount), 3D Specialists was contractually obligated to make necessary adjustments so that the Engineer approval would be obtained prior to receiving further progress payments.
He refused, demand to be paid up front. 3D Specialist’s contract was terminated for failure to perform.